Welcome to Our Site!
 

 

Progress Report > Package III - Electrical Works

As of July 31, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  134 of 780 (17.18%) Remaining 646days

Progress

 
 

- Continue the electrical conduit installation work at Southern Toll Plaza.

 

Photographs

Top

Construction Supervision

The Contractor continued with electrical works installations in North and South Toll Plaza buildings.  This is the only site work under this contract at this time. The majority of work at site is the preparation and submittal of shop drawings for toll plazas and the Vehicle Maintenance Building.

Coordination is ongoing between PKIII and PKIV for space, ventilation and cableway requirements at substations in the Electrostatic Precipitator areas (S/S 1, 2 and 4) and at the Ventilation Adit Building (S/S 6), S/S 3 at adit fresh air discharge near tunnel, and S/S 5 near north portal. This includes preparation of drawings.   Coordination is also being carried out at design stage for cable routes across Lang Co to be installed by PKIIA.

The Contractor continued to submit manufacturer's capability/certification materials and technical data for approval as suppliers of major systems and subsystems. The Contractor is in the process of increasing site based design support staff and the main design engineer for power distribution and control systems is scheduled to visit site next month (August) for design development discussions within the Contractor's staff and with the Engineer.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination