Construction Supervision Painting inside the building 80 % completed. Floor granite tiles tile 85 % completed. Door installation 95% completed. Window installation 95% completed. Air-condition installation 85% completed. Airfreight no. 6 and 7 arrived to site. 110 kV GIS installation completed. Diesel generator installation completed. Wiring Device installation 90% completed. HV Cable Installation is 100% completed LV Cable installation in Hai Van S/S 95% completed MV cable installation in Hai Van S/S completed. 110 kV Transmission Line stringing 85% completed. Steel structure erection in transition yard completed. Test on completion started.The
Contractor is continuing with civil/architectural works on the OCC
building. This work is months behind schedule and for more than one
month work crews have been very small thus extending completion time.
The air conditioning installation is still not complete. HV and MV cable
installation is complete. LV cable installation was 95% complete.
HV cable terminations were not completed because material parts (stress
cones) were incorrect and had to be replaced. All significant electrical
equipment items are now installed. GIS installation was complete with
the exception of one control/monitoring panel. The transmission line
from Tower No. 1 to Tower No. 14 was completed with the exception of the
OPGW wire. The transition yard steel erection is complete. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||