As of September 30, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

640 of 540 (118.51%) Extend 90days from June 20, 2003

Progress

 

110/22 kV Substation

Continue the civil work & finishing work for OCC Building.

110 kV Transmission Line

Start testing and commissioning

Photographs

110/22kV Substation Operation and Control Center Building
Power Distribution and Monitoring & Control System
110kV GIS High Voltage Test
Gantry Tower Installation in 110kV Power Transition Yard
110kV Cable Termination
Mr. Manh Secretary General Site Visit

Top

Construction Supervision

Painting inside the building 80 % completed.

Floor granite tiles tile 85 % completed.

Door installation 95% completed.

Window installation 95% completed.

Air-condition installation 85% completed.

Airfreight no. 6 and 7 arrived to site.

110 kV GIS installation completed.

Diesel generator installation completed.

Wiring Device installation 90% completed.

HV Cable Installation is 100% completed

LV Cable installation in Hai Van S/S 95% completed

MV cable installation in Hai Van S/S completed.

110 kV Transmission Line stringing 85% completed.

Steel structure erection in transition yard completed.

Test on completion started.

The Contractor is continuing with civil/architectural works on the OCC building. This work is months behind schedule and for more than one month work crews have been very small thus extending completion time. The air conditioning installation is still not complete. HV and MV cable installation is complete. LV cable installation was 95% complete.  HV cable terminations were not completed because material parts (stress cones) were incorrect and had to be replaced. All significant electrical equipment items are now installed. GIS installation was complete with the exception of one control/monitoring panel. The transmission line from Tower No. 1 to Tower No. 14 was completed with the exception of the OPGW wire.  The transition yard steel erection is complete.

Test and commissioning began with the GIS high voltage test and continued with scheduled tests on the GIS and the Control Room MicroSCADA. Contractor schedule is for commissioning completion late November. 

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination