Welcome to Our Site!
 

 

Progress Report > Package III - Electrical Works

As of October 31, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days) 617 of 780 (79.10%) Remaining 163 days

Progress

 

Installation of fire rated (FR) cable, supply cables for CCTV cameras, complete the installation work for area lighting floodlighting towers in NPP and NTP. Conduit was installed in sub-base at NPP and SPP for area lighting circuits.

Photographs

Lighting Pole Installation at South Bridge
Lighting Pole Installation at South Bridge
Lighting Pole Installation at South Bridge
Lighting Pole Installation at South Bridge
MV Cable Pulling Work at Main Tunnel
Warning Tape Installation work at NPP
Concrete Slab Installation Work at NPP
Equipment Installation at SS/5

Top

Construction Supervision

Summary from Contractor

The Contractor's site construction progress this month was less than previously. He is waiting for access to substation buildings to install major equipment that is already on site. A small amount of lighting and small power works in the VMB and toll plaza buildings was done. Tunnel works were limited to installation of brackets for the support of radio rebroadcast (RRB) coaxial antenna, fire sensor cable, and CCTV camera supports. Medium voltage (MV) cable pulling began at the end of October. Conduit and boxes continue to be installed in VAB as PKIV work progresses. Casting of pre-cast concrete foundations for road lighting poles continued.

Design work at site continues on the preparation and submittal of installation shop drawings. Detailed design continued in ABB Finland on systems (Fire alarm, and radio rebroadcast (RRB). Factory acceptance tests (FAT) were completed in early October in Finland on traffic control, lighting control, power distribution control, and main SCADA systems and on systems integration.

The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing. The south portal area duct banks were handed over in early July for PKIII installation of cable supports and to begin cable pulling in August. The north portal area duct banks were handed over on the 5th. August. Despite the Engineer's and civil contractors' efforts to support PKIII schedule, PKIII has failed to start installation of cable brackets inside manholes as of end of October.

PKIII took over maintenance of PKV works as provided for under their contract in May and were to negotiate to sub-contracted this work to HAMADECO. However HAMADECO declined to sign PKIII sub-contract agreement citing unacceptable insurance clauses. These clauses were copied from PKIII contract documents. PKIII will continue with maintenance of PKV works without sub-contractor.

Construction Supervision

Cable Pulling of Main Tunnel Lighting has been completed on the raceways.

Power Cable Pulling for Main Tunnel CCTV has been completed on the raceways.

Low Voltage cabling work at VMB has continued.

Low Voltage cabling work at S/S 5 has continued.

Lightning Protection System work at S/S 5 has completed.

Foundation for area lighting at NPP and NTP has been completed.

Low Voltage cabling work at STP has started

Building luminaries Installation work at STP has started.

Piping and Box Installation work at VAB has continued.

Cable trench excavation work for area lighting have been completed at SPP and NPP.

Batteries have been installed at SS5 and OCC

UPS have been installed at OCC

Installation of UPS, inverters and chargers have started in SS5.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination