Progress Report > Package IA - North Tunnel Section
Summary from Contractor The Concrete Lining for Standard Section of the Main Tunnel completed 3,857.00m (100%). In the Evacuation Tunnel, the casting of concrete for the side drainage completed 3,857m. For the Ventilation Adit, the second lift center wall commenced at the bottom VA station–071.05 and reached to 1+752.51 with a total length 1,823.56m. Construction Supervision by Engineer Main Tunnel Delineators was 100% completed Steel Covers for walkway along Niches was 100% completed Additional
road pavement markings are to be completed by January 2005 (98%) Evacuation Tunnel Base Course preparation at ET road pavement was 100% completed Emultion Penetration Pavement was 100% completed Delineators was 100% completed Doors installation for Vehicular Cross Passage was 100% completed North portal plaza Leachfield/other
incidental works at the North Portal Plaza are to be completed on
January (98% progress) Slope
protection work (additional work) for Cut and Cover is to be
completed by January (98% progress) Finishing
Works (i.e. guardrails, fence and gate, etc.) are planned for
completion by January (98% progress) Landscaping
(additional works) will be started after MOT’s decision. Ventilation Adit Tunnel Asphalt
Pavement was 100% completed Major Events and Issue This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||