As of December 31, 2004

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Contract period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1530 of 1460 (104.79%)

Progress

 

Main Tunnel(3857m)

Excavated 3857m in total (100%)

Concrete Lining: 3,857.00m (100%)

Evacuation Tunnel(3857m)

Excavated 3857m in total (100%)

Cast concrete for Side Drainage completed 3,847m

Ventilation Tunnel(1810m)

Excavated 1887.62m in total (100%)

Concrete Lining: 1,887.62m (100%)

Others

 

Photographs

North Portal Plaza
North Portal Plaza – Asphalt Pavement
North Portal Plaza – Boundary Fence Posts Installation
North Portal Plaza – Boundary Fence Installation
North Portal Plaza – Taking-over Inspection
North Portal Plaza – Taking-Over Inspection
Evacuation Tunnel – Taking-Over Inspection
Taking-Over Meeting

Top

Construction Supervision

Summary from Contractor

The Concrete Lining for Standard Section of the Main Tunnel completed 3,857.00m (100%).

In the Evacuation Tunnel, the casting of concrete for the side drainage completed 3,857m.

For the Ventilation Adit, the second lift center wall commenced at the bottom VA station–071.05 and reached to 1+752.51 with a total length 1,823.56m.

Construction Supervision by Engineer

Main Tunnel 

Delineators was 100% completed

Steel Covers for walkway along Niches was 100% completed

Additional road pavement markings are to be completed by January 2005 (98%)

Evacuation Tunnel

Base Course preparation at ET road pavement was 100% completed

Emultion Penetration Pavement  was 100% completed

Delineators was 100% completed

Doors installation for Vehicular Cross Passage was 100% completed

North portal plaza

Leachfield/other incidental works at the North Portal Plaza are to be completed on January (98% progress)

Slope protection work (additional work) for Cut and Cover is to be completed by January (98% progress)

Finishing Works (i.e. guardrails, fence and gate, etc.) are planned for completion by January (98% progress)

Landscaping (additional works) will be started after MOT’s decision.

Ventilation Adit Tunnel

Asphalt Pavement was 100% completed

Major Events and Issue

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination