As of March 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

906 of 1460 (62%) Remaining 554days

Progress

 

Main Tunnel(2417m)

151.55m in this month; 1,960.37m in total (82.40%)

Evacuation Tunnel(2429m)

104.55m in this month; 2,022.65m in total (83.89%)

Access Road to Water Reservoir.

Construction of drainage ditch – 330 m

Concrete road pavement – 65m

Bridge No.1(58m)

Foundation layer of North Abutment compacted

Others

 

 

Photographs

South Tunnel Portal

Construction of Cut and Cover Section

Fixing of Waterproofing Membrane

Construction of Foundation Beam

Placement of Concrete Lining by the First Formwork

Placement of Concrete Lining by the Second Formwork

Construction of Bench

Pull Out Test for Rockbolt

Construction of Evacuation Tunnel

Cross Passage No.6

Electrostatic Precipitator

Construction of West Slope

Abutment of Bridge No. 1

Top

Construction Supervision

Summary

During the reporting period 104.55m of Evacuation Tunnel and 151.55m of Main Tunnel Top Heading was excavated, giving a total length of 2022.65m of Evacuation Tunnel and 1960.37m of Main Tunnel Top Heading excavated to date.

Cross passage No. 6 was excavated.

Bench excavation continued with 138.16m being excavated on the West Side and 129.7m excavated on the East Side.

Tunnel lining continued with 333.22m of tunnel completed.

Excavation of the Electrostatic Precipitator continued with 75.44m excavated.

Tunnel lining was slightly down due to there being no waterproof membrane on site from the 11/3/03 until the 17/3/03.

Overall a good months progress with time gained against the original clause 14 construction schedule.  The Main Tunnel is four weeks behind schedule and Evacuation Tunnel nine weeks.

Evacuation Tunnel

A total of 104.55m of Evacuation Tunnel was excavated from St. 1+918.1 to St. 2+022.65 over the reporting period. Giving a total length of 2022.65m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Explosive:                                          6395 kg

Shotcrete 50mm thickness:                       1750.6 m2

Cross passage No. 6 – excavated 23.4m at St. 1+911.005

Explosive:                                          2025 kg

Shotcrete 100mm thickness:                                170 m2

Main Tunnel

A total of 151.55m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1960.37m of Main Tunnel Top Heading excavated to date.

Face No.7: 151.55m of Top Heading excavated from St. 1+808.82 to St. 1+960.37

Bench excavation 

 – 110.26m of bench excavated from St. 1+302.19 to St. 1+412.45 and 27.9m form St. 1+630 to St. 1+602.1 (West side).

– 129.7m of bench excavated from St. 1+350.9 to St. 1+480.6 (East side)

Electrostatic Precipitator Excavated 75.44m of tunnel from St. 0+087.7 to St. 0+137.78

Tunnel Lining

Concrete for Foundation Beam –147.86m Fr. St. 1+231.015 to St. 1+ 378.875 (West Side)

Concrete for Foundation Beam –206.636m Fr. St. 1+158.022 to St. 1+ 1+364.658 (East Side)

Concrete for Tunnel Lining – 333.216m (28 blocks) from St. 7+324.212 to St. 6+712.478

Installation of waterproofing membrane: 394 m                          

Access Road to Water Reservoir

Construction of drainage ditch – 330 m

Concrete road pavement - 65m

Major Events and Issues

On March 15, 2003: Delegation of Minister of Contruction, Mr. Nguyen Hong Quan visited the site.

On March 18, 2003, Delegation of Danang Road and Bridge Association visited the site.

On March 24, 2003, Delegation of Mr. Vu Bay, Deputy Manager of TCQM accompanied with Mr. Le Van Que, General Director of Song Da Corporation visited the site.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination