As of April 30, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

936 of 1460 (64.11%) Remaining 524days

Progress

 

Main Tunnel(2417m)

160.878m in this month; 2121.25 in total (89.16%)

Evacuation Tunnel(2429m)

142.85m in this month; 2165.5m in total (89.82%)

Access Road to Water Reservoir.

Construction of drainage ditch – 150 m

Bridge No.1(58m)

Foundation layer of North Abutment compacted

Others

 

 

Photographs

South Portal Area - April 2003
Drilling of Drainholes for West Slope
Installation of Rockbolt for West Slope
Installation of Formwork for Cross Passage at Km 0+180
Inspection of Double Welding Connection
Installation of Formwork for Fire-fighting Niche
Setting formwork No. 2
Construction of Face No.7
Erection of Formwork for Layby
Finishing of Formwork of Layby
Drilling Cores for Checking the Thickness of Support Shotcrete
Chairman of Vietnam Central Father-Front Committee visited the site
Chairman of Vietnam Central Father-Front Committee visited the site

Top

Construction Supervision

Summary

During the reporting period 142.85m of Evacuation Tunnel and 160.878m of Main Tunnel Top Heading was excavated, giving a total length of 2165.5m of Evacuation Tunnel and 2121.25m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 301.05m being excavated on the West Side and 156.3m excavated on the East Side.

Tunnel lining continued with 272.898m of tunnel completed.

Excavation of the Electrostatic Precipitator top heading was completed and bench excavation commenced.

The second main tunnel lining form (formwork No. 2) was removed from the main tunnel and the layby formwork was transported into the first layby, the first layby lining pour is scheduled for early May.

Overall a good months progress with time gained against the original clause 14 construction schedule.  The Main Tunnel is three weeks behind schedule and Evacuation Tunnel nine weeks.

Evacuation Tunnel

A total of 142.85m of Evacuation Tunnel was excavated from St. 2+022.65 to St. 2+165.5 over the reporting period. Giving a total length of 2165.5m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Explosive:                                          9140 kg

Shotcrete 50mm thickness:                       1224.6 m2

Main Tunnel

A total of 160.878m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2121.25m of Main Tunnel Top Heading excavated to date.

Face No.7:  160.878m of Top Heading excavated from St. 1+960.37 to St. 2+121.25

Bench excavation

– 301.05m of bench excavated from St. 1+412.45 to St. 1+713.5 (West side).

– 156.3m of bench excavated from St. 1+480.6 to St. 1+636.9 (East side)

Electrostatic Precipitator 

Completed excavation of top heading. 10m from St. 0+137.78 to St. 0+147.78  

Commenced excavation of bench.  67.668m of bench excavated from St. 0+008.582 to St. 0+076.25

Tunnel Lining

Concrete for Foundation Beam –174.55m Fr. St. 1+ 378.875 to St. 1+553.43 (West Side)

Concrete for Foundation Beam –192.442m Fr. St. 1+ 1+364.658 to St. 1+557.1 (East Side)

Concrete for Tunnel Lining – 272.898 (23 blocks) from St. 7+227.43 to St. 6+466.591

Installation of waterproofing membrane: 228 m                          

Access Road to Water Reservoir

Construction of drainage ditch – 150 m

Excavation of West Slope

Wire mesh CQS6:                                     226.96 m2           

Shotcrete grid:                                           226.96 m2

IBO rockbolts 6m:                                  27 No.

Drilling drain hole 114mm dia.:                80m/8No.

Major Events and Issues

- On April 1, 2003, the delegation of Reporter of the People Newspaper visited the site

- On April 6, 2003 the delegation of Central Vietnam Front Committee led by Mr. Pham The Duyet visited the site.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination