Welcome to Our Site!
 

 

Progress Report > Package III - Elctrical Works

As of March 31, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  44 of 780 (5.64%) Remaining 736days

Progress

 
  Total progress for site office facilities completed 50%

Photographs

Construction Supervision

The Contract Package commencement date was February 14, 2003 in conjunction with the L/C coming in force.

Down payment procedures were finalized and submitted to JBIC before the end of the Japanese fiscal year as requested by JBIC.

The Contractual Mobilization Plan was submitted to the Engineer and Employer on February 28, 2003. Approval of the Mobilization Plan was received on March 18, 2003.

Basic design criteria for communication system and traffic management have been submitted for approval on March 18, 2003. The Engineer has approved with comments on March 28 and 30, 2003 respectively.

The following key personnel have mobilized to site: Project Manager, Project Administrator, Power Distribution Site Supervisiors, Cabling and lighting site supervisors and assistants.

Top

/ Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination