Progress Report > Package III - Elctrical Works

As of April 30, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  44 of 780 (5.64%) Remaining 706 days

Progress

 
 

- Site office establishment

- Submission of staff mobilization plan, design of monitoring & control system

 

Photographs

Site office building
Site office building

 

Construction Supervision

During this month, the Contractor submitted 6 documents with design and manufacurer’s for approval. The extension of site office was completed. The Contractor continued to dicuss with the Engineer on the basic design criteria and principals of traffic control.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination