Construction
Supervision
Project
Schedule passed 26 months and 04 months remained from
the reporting month. Completion percentage was 75% based
on the activities completion (including 65% of bridge
work and 10% of road, Toll Plaza work and general
requirement work).
Bored
piling:
Total
218 nos of bored piles with different diameter are
required for foundation.
218
nos. of bored piles completed and completion
percentage of bored piling is 100%.
Substructure:
2
abutments and 25 piers are required for Lang Co
Bridge.
20
piers and 1 abutment completed up to cross head such
as P6 to P25 and South Abutment A2. North Abutment A1
remained.
Sheet
piles for pit excavation of P05, P04, P01 completed.
Pit excavation of P2 and P3 were under construction.
Superstructure:
Launching
of span 26 to span 13 (total 14 spans) completed.
Concrete of diaphragm of span above were completed
too.
Concrete
cast for Deck slab of those spans was carrying out but
have not completed yet. Deck slab of span 26, 25, 23,
22, 19, 18 completed the casting.
Approach
Road:
Granular
backfill behind the abutment A1, sub-grade layers and
mortar rip-rap were under construction. South approach
road completed the embankment.
Toll
plaza:
Toll
Plaza building were nearly completed, except the
building roof. Fence of the building and toll gate
were under construction
Girder
Production:
Total
130 nos. of PCI girders were required to produce. 1
place of girder prodction yard were under operation
only. T
Total
102 nos. of PCI girders completed the production.
Completion percentage of girder production was 78%.