As of August 31, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

610 of 540 (112.96%) Extend 90days from June 20, 2003

Progress

 

110/22 kV Substation

- Continue the civil work & finishing work for OCC Building.

110 kV Transmission Line

Complete the erection of 110kV Transmission Line Towers and start the 110kV Transmission Line stringing.

Photographs

110/22kV Substation Operation and Control Center Building
Waterproofing Work for OCC Building
Air-conditioning System Installation 
24kV Cable Termination
110kV Overhead Transmission Line ACSR Stringing Work

Top

Construction Supervision

During the last month the finishing work inside the building has continued and the equipment installation has proceeded. Outside the building painting work has continued. On the roof the waterproofing has been made. The manholes and cable ducts have been prepared for pulling the 110 kV cable. In the 110 kV GIS room and the in the control room the air-condition units have been installed.

During August shipment no. 11 arrived to site with the following equipment for Lien Chieu substation: Relay protection panel, control panel, marshalling box and SCADA communication and interface. Airfreight no. 2 to 5 arrived with tools and test equipment, which have been imported temporarily.

The installation of the 110 kV GIS has continued during last month.

The erection of the 110 kV Transmission Line towers is completed and the stringing is started. During the month of August the Transmission Line work was disturb by landowners claiming that the land acquisition is not solved.

The design for Lien Chieu Substation Modification has not been approved by EVN yet

Painting inside the building 70 % completed.

Floor granite tiles tile 75 % completed.

Door installation 95% completed.

Window installation 95% completed.

Access floor in Control room installation completed

Air-condition in 110 kV GIS room and control room completed.

Cable ladders 100% completed.

Shipment no. 11 delivered on site.

Airfreight no. 2-5 arrived to site.

110 kV GIS 75% completed.

Wiring Device installation 90% completed.

LV Cable installation in Hai Van S/S 85% completed

MV cable installation in Hai Van S/S 75% completed.

Diesel Generators 99% completed.

Cable duct and manholes 100% completed.

Erection of 110 kV Transmission Line Towers 100% completed.

110 kV Transmission Line stringing started

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination