Progress Report > Package IIA - Lang Co Bridge Section
Photographs Project
Schedule has already terminated. However, the Contractor
now want to extent the time but the official approval for
the extension has not issued yet. The completion
percentage was only 98.5% based on the completion of
activities (including 79.5% per total 80.6% of bridge work
and 19.0% per total 19.4% of road, Toll Plaza work and
general requirement work). Bored
piling: 100% completed. Substructure:
2 abutments and 25 piers are required for Lang Co Bridge.
25 piers and 2 abutments completed and completion
percentage was 100%. Superstructure: Launching of span 26 spans were completed and completion percentage was 100%. Concrete of Diaphragm of and deck slab all spans were completed. Parapet concrete cast for 26 spans completed. Railing was under installation. Drainage is under installation. Expansion Joint was not constructed yet. Approach
Road: Asphalt for the road was completed. Asphalt for
bridge was not constructed yet. Curb was under
construction now. Guardrail, transport sign and over high
barrier were not constructed yet. Toll
plaza: Toll Plaza building were completed general all.
Office equipment was not installed yet. Girder
Production: Completion percentage was 100%. Construction Supervision from the Engineer Bored piling:
Substructure:
Superstructure:
Approach Road:
Toll plaza:
Girder Production:
Mobilization of floating system