As of May 31, 2004

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

1050 of 900 (116.67%)

Progress

 

Approach Road and Lang Co Bridge (867m)

Completion percentage is 99% including 80% of bridge work and 19.0 of Road, Toll Plaza and general works.

Photographs

Top

Construction Supervision

Summary from Contractor

Project Schedule has already terminated. However, the Contractor now want to extent the time but the official approval for the extension has not issued yet. The  completion percentage was 99% based on the completion of activities (including 80% per total 80.6% of bridge work and 19.0% per total 19.4% of road, Toll Plaza work and general requirement work).

Bored piling: 100% completed.

Substructure: 100% completed.

Superstructure: Expansion Joint was not constructed yet.

Approach Road: Asphalt for the road was completed. Asphalt for bridge was not constructed yet. Curb was under construction now. Guardrail, transport sign and over high barrier were not constructed yet.

Toll plaza: Toll Plaza building were completed general all. Office equipment was not installed yet.

Girder Production: Completion percentage was 100%.

Construction Supervision from the Engineer

Bored piling: 

All bored piling machines were demobilized as the piling work was completed.

Substructure: 

Completed.

Superstructure: 

Drainage system was under construction.  Asphalt concrete for the bridge was not constructed yet. Painting work for Railing was under preparation.

Approach Road: 

Asphalt for road was completed. Asphalt for the bridge was not constructed yet. Curb was under construction. Guardrail, transport sign and over high barrier were not constructed yet.

Toll plaza: 

Toll Plaza building completed. Office equipment was not installed yet.

Girder Production: 

Completed 100%..

Mobilization of floating system

All floats with capacity 200 tons were demobilized..

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination