Construction
Supervision
Summary
from Contractor
Project
Schedule passed 28 months and 02 months remained from
the reporting month. Completion percentage was 88% based
on the activities completion (including 75% of bridge
work and 13% of road, Toll Plaza work and general requirement
work).
Bored
piling: Total 218 nos of bored piles with different
diameter are required for foundation. 218 nos. of bored
piles completed and completion percentage of bored piling
is 100%.
Substructure:
2 abutments and 25 piers are required for Lang Co Bridge.
22 piers and 2 abutments completed up to cross head
such as P1, P5 to P25. Cast of Pier P4 and P2 up to
top of column were completed. Excavation for footing
of P3 was completed.
Superstructure:
Launching of span 26 to span 10 (total 17 spans) were
completed. Concrete of diaphragm of span above were
completed too. Concrete cast for Deck slab of those
spans was carrying out but have not completed yet.
Approach
Road: Granular backfill behind the abutment A1 and A2,
sub-grade layers completed. South approach road completed
the embankment.
Toll
plaza: Toll Plaza building were completed. Fence of
the building and toll gate were under construction.
Concrete cast for roof of toll gate was under construction.
Girder
Production: total 130 nos. of PCI girders were required
to produce. 1 place of girder production yard were under
operation only. Total 120 nos. of PCI girders completed
the production. Completion percentage of girder production
was 92.3%.
Construction
Supervision from the Engineer
Bored
piling:
All
bored piling machines were demobilized as the
piling work was completed.
North
Abutment: 6 of 6 nos. of bored piles completed.
Pier
No.1: 4 of 4 nos. of bored piles was under construction.
However, one pile had problem during cast. Sonic Test
will be taken for final decision by the Engineer.
Pier
No.2: 4 of 4 nos. of bored piles completed.
Pier
No.3: 5 of 5 nos. of bored piles completed.
Pier
No.4: 4 of 4 nos. of bored piles completed.
Pier
No.5: 4 of 4 nos. of bored piles completed.
Pier
No.6: 5 of 5 nos. of bored piles completed.
Pier
No.7: 8 of 8 nos. of bored piles completed.
Pier
No.8: 8 of 8 nos. of bored piles completed.
Pier
No.9: 10 of 10 nos. of bored piles completed.
Pier
No.10: 9 of 9 nos. of bored piles completed.
Pier
No.11: 9 of 9 nos. of bored piles completed.
Pier
No.12: 12 of 12 nos. of bored piles completed.
Pier
No.13: 9 of 9 nos. of bored piles completed.
Pier
No.14: 10 of 10 nos. of bored piles completed.
Pier
No.15: 12 of 12 nos. of bored piles completed. However,
two piles No4 and No7 had trouble during cast that
pile cap plan changed and widen.
Pier
No.16: 10 of 10 nos. of bored piles completed.
Pier
No.17: 10 of 10 nos. of bored piles completed. Additional
pile No.7’ was constructed because Pile No.7 was rejected
due to the result of working record and sonic test.
Pier
No.18: 12 of 12 nos. of bored piles completed.
Pier
No.19: 10 of 10 nos. of bored piles completed.
Pier
No.20: 10 of 10 nos. of bored piles completed.
Pier
No.21: 12 of 12 nos. of bored piles completed.
Pier
No.22: 9 of 9 nos. of bored piles completed.
Pier
No.23: 9 of 9 nos. of bored piles completed.
Pier
No.24: 5 of 6 nos. of bored piles completed. 1 no.
of pile met boulder at – 2m from footing bottom and
could not drilling threw this boulder. This location
has been back filled by concrete.
Pier
No.25: 5 of 5 nos. of bored piles completed.
South
Abutment: 6 of 6 nos. of bored piles completed.
Substructure:
Abutment
A1: Concrete work completed. Concrete for Parapet
on Abutment was under construction.
Pier
No.1: Concrete cast of footing was completed and the
column was under construction.
Pier
No.2: Concrete was completed up to top of column.
Pier
No.3: Chipping of pile head was under construction.
Pier
No.4: Concrete was completed up to top of column.
Pier
No.5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17,
18, 19, 20, 21, 22, 23, 24:
Concrete
work completed up to cross head
South
Abutment: Concrete work was completed. Concrete for
parapet on abutment was under construction.
Superstructure:
Launching
work for spans from 26 to span 10 (total 17 spans)
was completed. Concrete of diaphragm of spans above
were completed too. Concrete cast for deck slab of
those spans was nearly completed.
Approach
Road:
Granular
backfill behind abutment A1, A2 and all subgrade layers
completed.
Mortar
rip-rap were under construction. South approach road
completed the embankment.
Toll
plaza:
Toll
Plaza building was nearly completed. Fence of building
and toll gate were under construction.
Girder
Production:
Total
130 nos. of PCI girders need to produce.
1
place of girder production yard was under operation
only. The yard next to abutment A2 was not used. Total
of 120 nos. of PCI girders were completed the production.
Completion percentage of girder production was 92.3%.
Mobilization
of floating system
5
nos. of float completed the erection at site and they
were used for construction of piers in river.