Welcome to Our Site!
 

 

As of October 31, 2003

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

840 of 900 (93.33%) Remaining 60 days

Progress

North Approach

Mortar riprap under construction and 3 layers of subbase
completed.

Lang Co Bridge (867m)

Substructure: 22 piers and 2 abutments completed up to cross head. Excavation for footing of P3 completed.
Superstructure: Launching and concrete of diaphragm of span 26 to span 10 (17 span) completed.

South Approach

Embankment completed

Photographs

Top

Construction Supervision

Summary from Contractor

Project Schedule passed 28 months and 02 months remained from the reporting month. Completion percentage was 88% based on the activities completion (including 75% of bridge work and 13% of road, Toll Plaza work and general requirement work).

Bored piling: Total 218 nos of bored piles with different diameter are required for foundation. 218 nos. of bored piles completed and completion percentage of bored piling is 100%.

Substructure: 2 abutments and 25 piers are required for Lang Co Bridge. 22 piers and 2 abutments completed up to cross head such as P1, P5 to P25. Cast of Pier P4 and P2 up to top of column were completed. Excavation for footing of P3 was completed.

Superstructure: Launching of span 26 to span 10 (total 17 spans) were completed. Concrete of diaphragm of span above were completed too. Concrete cast for Deck slab of those spans was carrying out but have not completed yet.

Approach Road: Granular backfill behind the abutment A1 and A2, sub-grade layers completed. South approach road completed the embankment.

Toll plaza: Toll Plaza building were completed. Fence of the building and toll gate were under construction. Concrete cast for roof of toll gate was under construction.

Girder Production: total 130 nos. of PCI girders were required to produce. 1 place of girder production yard were under operation only. Total 120 nos. of PCI girders completed the production. Completion percentage of girder production was 92.3%.

Construction Supervision from the Engineer

Bored piling: 

All bored piling machines  were demobilized as the piling work was completed.

North Abutment: 6 of 6 nos. of bored piles completed.

Pier No.1: 4 of 4 nos. of bored piles was under construction. However, one pile had problem during cast. Sonic Test will be taken for final decision by the Engineer.

Pier No.2: 4 of 4 nos. of bored piles completed.

Pier No.3: 5 of 5 nos. of bored piles completed.

Pier No.4: 4 of 4 nos. of bored piles completed.

Pier No.5: 4 of 4 nos. of bored piles completed.

Pier No.6: 5 of 5 nos. of bored piles completed.

Pier No.7: 8 of 8 nos. of bored piles completed.

Pier No.8: 8 of 8 nos. of bored piles completed.

Pier No.9: 10 of 10 nos. of bored piles completed.

Pier No.10: 9 of 9 nos. of bored piles completed.

Pier No.11: 9 of 9 nos. of bored piles completed.

Pier No.12: 12 of 12 nos. of bored piles completed.

Pier No.13: 9 of 9 nos. of bored piles completed.

Pier No.14: 10 of 10 nos. of bored piles completed.

Pier No.15: 12 of 12 nos. of bored piles completed. However, two piles No4 and No7 had trouble during cast that pile cap plan changed and widen.

Pier No.16: 10 of 10 nos. of bored piles completed.

Pier No.17: 10 of 10 nos. of bored piles completed. Additional pile No.7’ was constructed because Pile No.7 was rejected due to the result of working record and sonic test.

Pier No.18: 12 of 12 nos. of bored piles completed.

Pier No.19: 10 of 10 nos. of bored piles completed.

Pier No.20: 10 of 10 nos. of bored piles completed.

Pier No.21: 12 of 12 nos. of bored piles completed.

Pier No.22: 9 of 9 nos. of bored piles completed.

Pier No.23: 9 of 9 nos. of bored piles completed.

Pier No.24: 5 of 6 nos. of bored piles completed. 1 no. of pile met boulder at – 2m from footing bottom and could not drilling threw this boulder. This location has been back filled by concrete.

Pier No.25: 5 of 5 nos. of bored piles completed.

South Abutment: 6 of 6 nos. of bored piles completed.

Substructure: 

Abutment A1: Concrete work completed. Concrete for Parapet on Abutment was under construction.

Pier No.1: Concrete cast of footing was completed and the column was under construction.

Pier No.2: Concrete was completed up to top of column.

Pier No.3: Chipping of pile head was under construction.

Pier No.4: Concrete was completed up to top of column.

Pier No.5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24:

Concrete work completed up to cross head

South Abutment: Concrete work was completed. Concrete for parapet on abutment was under construction.

Superstructure: 

Launching work for spans from 26 to span 10 (total 17 spans) was completed. Concrete of diaphragm of spans above were completed too. Concrete cast for deck slab of those spans was nearly completed.

Approach Road: 

Granular backfill behind abutment A1, A2 and all subgrade layers completed.

Mortar rip-rap were under construction. South approach road completed the embankment.

Toll plaza: 

Toll Plaza building was nearly completed. Fence of building and toll gate were under construction.

Girder Production: 

Total 130 nos. of PCI girders need to produce.

1 place of girder production yard was under operation only. The yard next to abutment A2 was not used. Total of 120 nos. of PCI girders were completed the production. Completion percentage of girder production was 92.3%.

Mobilization of floating system

5 nos. of float completed the erection at site and they were used for construction of piers in river.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination